St Paul’s Way Infant School – Public Sector – Education
Project Particulars
- CONVERSION SCHEME – CHANGE OF USE
- INTERNAL REMODELLING
- IPS
- INTERNAL FIT OUT
Case Study
The scheme involved the conversion of the existing Burdett Community Centre building into St Paul’s Way Infant School.
Works comprised of:
– The internal remodelling; including partitions, ceilings and finishes
– The design and installation of IPS cubicles to create WC facilities and bespoke vanity units
– The creation of a hygienic commercial kitchen area
– Structural works and alterations including steel work, create openings, and trimming to the existing floor structure
– Contract Value: £100,000
– Contract Programme: 12 Weeks